Wind power: Ethiopia beats Kenya to the finish line.
Ashegoda windfarm: The largest wind project in Africa |
Kenya has very
ambitious plans, including being home to Africa’s largest wind power project, the
Lake Turkana Wind power Project, which is just crawling off the ground. Other projects include the proposed 100MW
Kipeto Energy sponsored by the American multinational GE in the Ngong area at a
cost of US$ 300 million; Aeolus (Kinangop and Ngong Hills) and Isiolo Wind
farm.
The Ashegoda project in Ethiopia cost US$ 290 million was built by French firm Vergnet SA was funded by concessional
loans from BNP Paribas and the French Development Agency (AFD). The Ethiopian
government contributed 9 percent of the cost.
This follows the
commissioning of 51MW Adamia1 wind farm in 2011. The project was built by Hydro
China and CGOC also of China at a cost of US$117 million. It was funded by the
Chinese Export Import Bank and the Ethiopian government.
The progress of Ethiopian power development is an important
lesson for African countries. Power generation is still the preserve of the
government owing to its large capital outlay. All Ethiopian Power projects
enjoyed a significant (9-15 per cent of the project cost) financial input from
the government. The government, through a bond meant for Ethiopians will fund
the US$4.8 billion 6,000MW Grand Ethiopian Renaissance Dam GERD, currently
under construction at the Blue Nile.
This is the lesson Kenya appears to have learnt in the development
of geothermal. The private sector has no stomach for the drilling risk nor does
the financial sector appear ready to finance such a risky venture. Therefore,
where the energy sector is liberalized as in Kenya, the government has to bear
the drilling risk and then allow the private sector to generate power from the
capped wells. That has resulted in a rapid expansion of geothermal power
generation in Kenya, which could reach at least 1000MW by 2016.
Participation of the government is a confidence builder especially
for the private sector financiers. Refusal by the Kenya government to provide
sovereign risk on the Lake Turkana wind power project, which will generate
300MW thus being the largest such project in Africa, has resulted in its lengthy
delays.
However, the project
is back on track after the Africa development Bank issued guarantees for the
construction of the 400kv, 428km high voltage transmission line to deliver
electricity from the site to Suswa station. Lack of sovereign guarantees was one of the causes for the delay.
The wind farm is located in a very remote area lacking in basic infrastructure. Initially LWTP was expected to build the infrastructure including the transmission line to Sasumua power station 400km away. This is in addition to building roads to transport the generating equipment.
However, several government interventions have eased the burden on the sponsors, making the project attractive to investors. One of the interventions was the decision by the government to build the transmission line.
Comments
Post a Comment